Here's a title built to be skipped: "Finger Joints and Miscellaneous Steel Repairs at The Verrazzano-Narrows Bridge." MTA Construction & Development advertised it today for MTA Bridges and Tunnels — VN-9A, CR#2138178. Documents went orderable Friday, bids open September 23, and the clock runs 1,005 calendar days. Two years, nine months. For joints.
So why three years? Because the bridge moves. From B&T's own facts page: "Seasonal contractions and expansions of the steel cables cause the double-decked roadway to be 12 feet lower in the summer than in the winter." Twelve feet — August against January. A finger joint is what absorbs that: two combs of steel plate that interleave and slide in and out of each other like laced fingers, while traffic rolls over the top.
“That roadway rides twelve feet higher in February than it does today — and the fingers are the only part that knows it.”
And they get big. The joint maker's published record on this bridge calls VNB joints "generally of the sliding finger type," the largest handling 2,700 millimeters of deck movement — nine feet, damn near a lane width. That type "is no longer used in modern bridge construction — except where required to replace an existing joint of the same type." So you're not buying a catalog part. You're buying custom steel cut to existing geometry, trial-assembled off site before it ships. (That record covers VNB joints generally; no supplier or rating is published for VN-9A.)
Published terms: an IFB in a $10 million to $50 million band, 100 percent MTA capital, goals of 15 percent MBE, 15 percent WBE, 6 percent SDVOB. Scope is the lower-level tower side span finger plates at the Brooklyn and Staten Island towers, roadway drainage and new access doors at both anchorages, saddle-room ladder retrofits, and tower span steel painting. Two towers, two anchorages, four trades, no published quantities — those sit in the documents, which need an MTA Bidder/Supplier number, SAM registration and your NYSDOL 220-i certificate.
Our arithmetic on MTA's figures, not MTA's characterization: $50 million across 1,005 days is under $50,000 of work a day, under $10,000 at the floor of the band. Three years on a mid-size number isn't steel volume — it's access on a live double-deck crossing. VN-9A's own access restrictions aren't published.
Which is why it's A+B: you price the work (A), you bid the schedule (B) with time converted to dollars, and the low total evaluated bid wins. On AW-9Y, opened August 12, TDP Associates took low at $18,521,000 — $11,506,000 of work plus $7,015,000 of time. On TN-9A at the Throgs Neck, El Sol Contracting/ES II Enterprises JV took low at $149,674,992 against Ahern Painting's $157,546,909 and Kiewit's $192,962,000, with B running about 20 percent of the total. El Sol bid the longest time of the three and still came out low, on a lower A.
The contract number is the capital line. VN-9A decodes to element D901VN9A, carrying $61.59 million in the 2025-2029 plan — so this package is 16 to 81 percent of its own element. Normal draw, not a hidden mega-package.
It's also EUCI eligible — MTA's Enhanced Utilization Credit, "an additional fifty percent (50%) credit" for MWBE firms with limited or no prior MTA work. Say you bid $30 million: a 15 percent MBE goal is $4.5 million. Buy $2 million of it from an EUCI-eligible sub and it counts as $3 million.
Now the part that hurts. Three NYC-region bridge-steel packages close inside eight days: NYSDOT's Owl's Head Viaduct rehab over 61st Street in Brooklyn on September 16, NYSDOT's Robert Moses Causeway painting and steel repairs over Great South Bay on September 17, VN-9A on September 23. Neither DOT job publishes a dollar figure. And the bench repeats — El Sol/ES II, Ahern, TDP, Kiewit, over and over on B&T tabs.
There's no plan-holder list to read here — the portal link is shared with another contract and returns a placeholder, and the docs have only been orderable four days, so it tells you nothing about interest. The August 27 Teams pre-bid and the August 28 site tour at 1 Verrazzano Bridge Plaza aren't mandatory. Go anyway. That roadway rides twelve feet higher in February than it does today, and the fingers are the only part that knows it.