The Department of Design and Construction registered a $26,890,000 contract with P&T II Contracting Corp for non-standard pedestrian ramp construction, according to NYC Comptroller's Checkbook NYC.
The contract, awarded through competitive sealed bidding, runs from November 1, 2026 to October 30, 2028 — just under two years of work. Checkbook NYC lists it as a non-M/WBE award under PIN 85026B0061001.
Pedestrian ramp work is DDC's bread-and-butter infrastructure category: curb cuts, ADA-compliant corner reconstructions, and drainage tie-ins across the five boroughs, usually bid as standing citywide contracts rather than site-specific jobs. A contract this size, running two years, typically means the agency is drawing against it job by job as individual street segments get scheduled — the kind of steady, lower-margin volume work that keeps a sidewalk and concrete outfit staffed between bigger jobs.
P&T II Contracting Corp's win here is the only one of its kind in this registration batch — the other two new contracts logged the same week are a $380,000 waste yard job and a $2.74 million pool filter plant job, both far smaller in scope and duration.
No subcontracting goals or M/WBE participation requirements are listed on this contract in the Checkbook record.