Three upstate New York towns moved to block large-scale data centers from breaking ground within their borders this week, adding to a list of local governments writing their own rules while the state's own pause sits unresolved.
The Hamburg Town Board, in Erie County, enacted a moratorium on large-scale data centers, according to The Buffalo News. In Tompkins County, the Lansing Town Board was set to vote on a data center ban, the Cornell Daily Sun reported. And in St. Lawrence County, the Potsdam Town Board passed a moratorium covering both data centers and cryptocurrency mining operations, the Watertown Daily Times reported.
None of the three actions overlaps with Governor Hochul's Executive Order 62, the statewide pause on new data centers that can consume 50 megawatts or more signed July 14. That order runs only until the Department of Public Service finishes its environmental review, and it does not touch local zoning power at all — a town can ban data centers outright, or allow them, independent of what Albany decides on the megawatt threshold.
That gap is the whole story for anyone bidding this work. A site can clear the state's 50-megawatt test, or sit under it entirely, and still be dead on arrival the moment a town board votes. Hamburg, Lansing and Potsdam are small jurisdictions, but they are exactly the kind of exurban and rural townships hyperscale developers have been targeting for land and power access — the same places a contractor might have been quietly tracking for sitework, substation, or structural-steel scope.
Connecticut is moving on a parallel but separate track. State lawmakers are discussing an outright ban on new data centers, according to the UConn Daily Campus, on top of the bring-your-own-power requirement at 20 megawatts and up already under discussion there. No vote has been reported yet in Connecticut; the upstate New York moratoriums have actually passed or are scheduled for a vote, which is a meaningfully different stage.