New York City's Department of Buildings served 32 Environmental Control Board violations dated November 10 and 11 against construction sites and buildings across the five boroughs, according to DOB ECB violation records. Hearings on the new violations are scheduled for January 14 through January 21, 2027.

Two of the violations stem from a worker fall at a Manhattan high-rise under construction. DOB inspectors responding to an incident at 111 West 33rd Street in Manhattan found a worker had fallen from a ladder while drilling a hole in a ceiling, according to ECB violation records citing respondent JRM Construction Mgmt LLC. One violation, carrying a $1,250 penalty, cites inadequate housekeeping — metal studs not properly stored and an uncleaned floor — as a contributing condition under Building Code 3303.4. A second violation, carrying a $2,500 penalty, states the ladder itself "were in an unsafe condition with bent and twisted rear rungs that compromised its" stability, per the violation record. Both are Class 1 or Class 2 violations and remain pending.

A separate violation records a piece of marble panel that fell from the roof level of a 43-story building at 999 on Block 00999 in Manhattan, striking a car on the street below. DOB records list the respondent as Structural Preserv System, a Columbia, Maryland-based firm, and the $10,000 penalty violation states inspectors found "no adequate safety measu[res]" in place at the time, citing Building Code 3301.2 for failure to safeguard persons and property affected by construction operations.

The largest concentration of new violations hit a single six-story new-building site at 6701 Bay Parkway in Brooklyn, where DOB records list five separate violations issued the same day against respondent Abeco Construction LLC. Inspectors cited the site for scissor-lift workers without manufacturer certification on hand, a "backers scaffold on various floors" installed without outriggers or guardrails and with workers lacking personal protective equipment, a supported pipe scaffold missing full planking, guardrails, mudsills and screw jacks, an unpermitted concrete washout box placed in the street, and materials stored on the sidewalk without required plywood barriers. Penalties at the address total $20,000 across the five violations, all pending hearings set for January 20, 2027.

A 12-story new-building site at 670 Myrtle Avenue in Brooklyn drew five violations against respondent Lead It Builders LLC, including a standpipe that DOB records say extended only to the 8th floor on a building more than 94 feet high during concrete operations on the 11th floor, a supported scaffold system positioned roughly 10 feet below the working deck without a guardrail system, missing roof protection roughly 30 feet above an adjacent property, standing water in the cellar, and construction equipment and a generator stored in the roadway without an active DOT permit. Penalties there total $17,500, with hearings scheduled for January 15, 2027.

In Brooklyn, a boiler installation at 2721 Snyder Avenue drew two violations against respondent Carlton McGarrell totaling $25,000 — one for a boiler DOB records describe as "installed inadequately" at the cellar level, filed in response to an incident, and a second citing work without a permit for the swap of one boiler model for another. In Queens, a four-story new-building topping out at roughly 50 feet at 131-44 40 Road drew three violations against Acer Construction Inc totaling $12,300, including a missing sidewalk shed and inadequate roof protection with missing planks, per DOB records.

None of the violations carry a stop-work order in the records reviewed, and all list "PENDING" hearing status with penalties unpaid as of the issue date. DOB's violation database is updated continuously; respondents may contest penalties at the scheduled OATH/ECB hearings.