The U.S. General Services Administration will not consider an offer on its Thurgood Marshall U.S. Courthouse elevator job unless the offer includes a price under a project labor agreement, according to the solicitation for contract 47PB5126R0018. Proposals are due by 4:00 PM Eastern on December 4.
The solicitation calls it a paired-proposal procedure. Every offeror must submit a price with a project labor agreement. An offeror may also submit a second price without one, for the same scope. The two must match except for the agreement and its direct effects on cost, schedule or approach. A firm that does not submit the labor-agreement price is "ineligible for award," the document says.
The solicitation also says how GSA will compare the two prices. The agency will first decide whether the added cost of the labor agreement is reasonable. To do that, it will reduce the labor-agreement price by 10% or $15 million, whichever is less, and use that figure in its comparison. A premium above that amount "may be found non-reasonable," the document says, and in that case GSA will use the price without the agreement.
The same document puts the estimated price range at $30 million to $40 million. GSA's notice for the job on SAM.gov gives a range of $20 million to $40 million.
Amendment 1, dated October 16, cut the schedule nearly in half. The time to reach substantial completion went from 2,580 calendar days to 1,440 calendar days after notice to proceed. The amended schedule runs the base work from June 15, 2027 to May 25, 2031, with 60 days of closeout after that. The agreement sets liquidated damages at $3,193.70 per calendar day.
The base contract covers 13 public elevators, according to the agreement: units 1 through 4, 6 through 9 and 11 through 15. The contractor removes the old equipment and installs new gearless traction machines, microprocessor-based controllers, car and hoistway door equipment and signal fixtures, and ties the elevators into the building's telecom and security systems. Six options sit on top of the base. Four of them cover elevators 18 through 21, each priced as its own line. The other two cover destination dispatch and what the price form calls toggle bolt work.
Price is not the main test. The solicitation says the four non-price factors, taken together, are "significantly more important" than price. Experience on similar projects counts for 30%, management approach for 30%, past performance for 20% and the logistics plan for 20%. GSA says a project is more similar if it was an elevator modernization worth $20 million or more, finished in the last seven years, in an occupied and secure building. The agency also says it will not perform a price realism analysis. The bid guarantee is 20% of the price or $3 million, whichever is less.
Amendment 2, dated November 4, posted the sign-in sheets from the October 22 pre-proposal conference and the October 27 and 28 site visits. The two sheets name 23 firms. Schindler Elevator Corporation, Mid-American Elevator Company, Inc., TEI Group and Atta Elevators New York Inc. signed in to the conference as subcontractors. Forte Construction Corp., Prismatic Development Corporation, Volmar Construction Inc., Peter Scalamandre & Sons, Inc. and PKD, Inc. were among the firms that signed in as primes.
The specifications, the drawing set and the conference slides are controlled attachments on SAM.gov. GSA requires access authorization before a firm can open them. Neither amendment extended the December 4 deadline.
What to do next
If you are pricing this job as a prime, build the labor-agreement price first, because an offer without it cannot win. Request the controlled drawings and specifications through SAM.gov now, and acknowledge both amendments on the offer form. If you are an elevator, electrical or mechanical sub, the sign-in sheets posted with Amendment 2 are your list of primes to call before December 4.