Design and Construction took bids on New York City Center Chiller Replacement. Bids were due Thursday, September 24, 2026.
| Listed as | PV279ACON New York City Center Chiller Replacement |
| Agency | |
| Solicitation | 85026B0114 |
| Bids due | September 24, 2026 — Bids due 2:00 PM; opening 2:30 PM. |
| Est. value | $4,211,064.80 (agency estimated procurement value) |
| Status | Closed — this listing is no longer open |
| First listed | August 18, 2026 |
| Record | RFI-000010 |
Update, Sept. 16: DDC postponed this bid one week, from Sept. 17 to Thursday, Sept. 24, with the opening at 2:30 p.m. The job replaces the rooftop chiller at New York City Center and the air handlers in the 4th through 6th floor mechanical rooms, with new louvers on the 56th Street side and supporting structural, electrical and plumbing work. An addendum with revised drawings is out. Agency estimate is about $4.2 million.
Part of New York City Center Chiller Replacement: the agency bid, every request for subs and the plan holders on this job, on one page.
City Record Online (CROL) → The live bid board
Every open bid and bid result from Design and Construction, with how the owner lets its work and where to register.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire