8 firms bid on PROJECT OBJECTIVE IS TO REDESIGN THE HVAC SYSTEM TO PROVIDE COMFORTABLE TEMPERATURE CONTROL THROUGHOUT THE BUILDING, WHILE IMPROVING ENERGY USE AND REDUCING EMISSIONS. for NYC DDC; bids were opened on Monday, October 19, 2026. PEN ENTERPRISES INC. was the apparent low bidder at $10,712,899. The next bid was $11,476,549, 7.1% higher. The low bid was 21.3% under the engineer's estimate of $13,605,688. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | |
| Solicitation | 8502026PV0015C |
| Trade | General Construction |
| Bids opened | October 19, 2026 |
| Bidders | 8 |
| Apparent low | PEN ENTERPRISES INC. — $10,712,899 |
| Engineer's estimate | $13,605,688 |
| Spread | 7.1% (second-low vs. low) |
| First listed | October 27, 2026 |
| Record | RFI-005028 |
Apparent low bidder: PEN ENTERPRISES INC. at $10,712,899.49 — preliminary per DDC, subject to verification and not yet a confirmed award. 8 bids received. DDC engineer's estimate: $13,605,688.35.
| Bidder | Bid |
|---|---|
| PEN ENTERPRISES INC. | $10,712,899 |
| AWL INDUSTRIES, INC | $11,476,549 |
| ACS SYSTEM ASSOCIATES, INC | $12,021,449 |
| CDE AIR CONDITIONING CO. | $12,352,979 |
| ENL MECHANICAL INCORPORATED | $12,444,000 |
| DYNAMIC US INC | $13,172,649 |
| NEELAM CONSTRUCTION CORP. | $14,807,374 |
| LANMARK GROUP, INC. | $16,861,968 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
NYC DDC construction contracts (preliminary bid results & awards) → The live bid board
Every open bid and bid result from NYC DDC, with how the owner lets its work and where to register.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire