Bid Result
18 firms bid on CUNY Herbert H. Lehman College Campus Central Bridge and Concert Hall Entry Plaza Restoration for Dormitory Authority of the State of New York; bids were opened on Thursday, December 5, 2024. High Point Construction Group Corp. was the apparent low bidder at $3,675,786. The next bid was $4,744,991, 29.1% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | Dormitory Authority of the State of New York |
| Solicitation | 3497009999CRNO.16 |
| Location | Bronx, NY |
| Bids opened | December 5, 2024 |
| Bidders | 18 |
| Apparent low | High Point Construction Group Corp. — $3,675,786 |
| Spread | 29.1% (second-low vs. low) |
| First listed | October 20, 2026 |
| Record | RFI-004448 |
Bids opened December 5, 2024. 18 bids. Apparent low bidder: High Point Construction Group Corp. at $3,675,786. Award not yet confirmed.
| Bidder | Bid |
|---|---|
| High Point Construction Group Corp. | $3,675,786 |
| Pb Contracting Corp. | $4,744,991 |
| Singh Landscaping & Lawn Sprinkler Corp. | $4,759,975 |
| ZHN Contracting Corp | $5,813,349 |
| Granite Environmental Services Inc | $5,963,045 |
| B N Restoration Inc. | $5,992,786 |
| Sea Breeze General Const. Inc. | $6,059,410 |
| SRR Holdings LLC | $6,873,714 |
| LO SARDO General Contractors, Inc. | $6,993,000 |
| Fidelis Contracting Inc. | $7,227,525 |
| Constructomics LLC | $7,692,780 |
| Atlantic Specialty Inc | $7,988,690 |
| Avenue Contracting Inc. | $8,610,781 |
| Olympic Contracting Corp. | $8,950,000 |
| Padilla Construction Services, Inc | $8,996,542 |
| Metropolitan Construction Corp. | $9,630,935 |
| Navillus Contracting d/b/a Navillus Tile, Inc. | $9,799,000 |
| Lanmark Group, Inc | $10,585,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
camelotplanroom.com → The live bid board
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire