Bid Result

Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction

10 firms bid on Bushwick Inlet Park Motiva Parcel Remediation and Passive Seating Area Construction for NYC Department of Parks and Recreation; bids were opened on Wednesday, December 20, 2023. William A. Gross Construction Associates, Inc. was the apparent low bidder at $6,145,000. The next bid was $7,240,381, 17.8% higher. The apparent low bidder is not the awardee until the owner makes the award.

AgencyNYC Department of Parks and Recreation
Solicitation84623B0078
LocationBrooklyn, NY
Bids openedDecember 20, 2023
Bidders10
Apparent lowWilliam A. Gross Construction Associates, Inc. — $6,145,000
Spread17.8% (second-low vs. low)
First listedOctober 20, 2026
RecordRFI-004297

Bids opened December 20, 2023. 10 bids. Apparent low bidder: William A. Gross Construction Associates, Inc. at $6,145,000. Award not yet confirmed.

BidderBid
William A. Gross Construction Associates, Inc.$6,145,000
J.Pizzirusso Landscaping Corp dba JPL Industries$7,240,381
Steven Dubner Landscaping & Construction$7,521,485
Perfetto Enterprises Company Inc.$7,825,059
AAH Construction Corp.$7,849,015
Difazio Industries, Inc.$7,965,966
Deborah Bradley Construction & Management Services$7,990,939
Perfetto Contracting Co Inc.$8,302,550
JRCRUZ Corp$8,625,768
Paul J. Scariano, Inc dba PJS Electric Inc.$8,675,309

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.