Home › The RFP Wire › RFI-004092
Bid Result
20 firms bid on CUNY York College Health and Physical Education Complex (HPEC) ADA Toilet Upgrade and Associated Asbestos Abatement for Dormitory Authority of the State of New York; bids were opened on Wednesday, February 21, 2024. Bluestone Developers Inc was the apparent low bidder at $2,973,167. The next bid was $3,508,648, 18% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | Dormitory Authority of the State of New York |
| Solicitation | 3584209999CRNO.13 |
| Location | Queens, NY |
| Bids opened | February 21, 2024 |
| Bidders | 20 |
| Apparent low | Bluestone Developers Inc — $2,973,167 |
| Spread | 18% (second-low vs. low) |
| First listed | October 20, 2026 |
| Record | RFI-004092 |
Bids opened February 21, 2024. 20 bids. Apparent low bidder: Bluestone Developers Inc at $2,973,167. Award not yet confirmed.
| Bidder | Bid |
|---|---|
| Bluestone Developers Inc | $2,973,167 |
| Saheet Construction Corp. | $3,508,648 |
| Vernon Construction & Development | $4,684,000 |
| Oudaz General Contracting Inc | $4,898,000 |
| Empire Control Abatement, Inc. | $4,905,000 |
| Gryphon Construction Inc. | $4,934,092 |
| VREX Remodeling and Construction Inc | $4,985,943 |
| Five Star Contracting Companies Inc | $5,200,000 |
| Fidelis Contracting Inc. | $5,265,000 |
| SRR Holdings LLC | $5,328,786 |
| United Force Construction Corp. | $5,380,000 |
| ACS System Associates, Inc. | $5,395,000 |
| Atlantic Specialty Inc | $5,678,000 |
| Pb Contracting Corp. | $5,790,000 |
| Constructomics LLC | $5,886,530 |
| Attri Enterprises Inc. | $6,727,000 |
| Cube Construction Services LLC | $6,766,799 |
| CVM Construction Corp | $6,900,000 |
| Olympic Contracting Corp. | $7,396,000 |
| National Environmental Safety Company, Inc. | $7,588,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.