6 firms bid on Katherine R. Snyder PS 222 (K) FY21 Reso A Playground Upgrade for NYC School Construction Authority; bids were opened on Tuesday, April 16, 2024. Honey Construction NY, Inc was the apparent low bidder at $563,111. The next bid was $569,970, 1.2% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | NYC School Construction Authority |
| Solicitation | 24-20924D |
| Location | Brooklyn, NY |
| Bids opened | April 16, 2024 |
| Bidders | 6 |
| Apparent low | Honey Construction NY, Inc — $563,111 |
| Spread | 1.2% (second-low vs. low) |
| First listed | October 20, 2026 |
| Record | RFI-003873 |
Bids opened April 16, 2024. 6 bids. Apparent low bidder: Honey Construction NY, Inc at $563,111. Award not yet confirmed.
| Bidder | Bid |
|---|---|
| Honey Construction NY, Inc | $563,111 |
| VAM Builders Inc. | $569,970 |
| Satnaam International Construction Corp. | $729,000 |
| N.B.A Construction Inc | $770,000 |
| Leading Construction Corp | $784,999 |
| Rizvi Builders USA Inc. | $1,098,460 |