Phase 2 Building Upgrades at Tuttle Avenue Elementary School

4 firms bid on Phase 2 Building Upgrades at Tuttle Avenue Elementary School for Eastport-South Manor Central School District; bids were opened on Monday, August 12, 2024. Ashlar Contracting was the apparent low bidder at $240,000. The next bid was $297,500, 24% higher. The apparent low bidder is not the awardee until the owner makes the award.

AgencyEastport-South Manor Central School District
SolicitationH2MESSD2305
LocationSuffolk County, NY
Bids openedAugust 12, 2024
Bidders4
Apparent lowAshlar Contracting — $240,000
Spread24% (second-low vs. low)
First listedOctober 20, 2026
RecordRFI-003790

Bids opened August 12, 2024. 4 bids. Apparent low bidder: Ashlar Contracting at $240,000. Award not yet confirmed.

BidderBid
Ashlar Contracting$240,000
SJS Construction Company, Inc.$297,500
Stalco Construction, Inc.$457,000
Preferred Construction Inc.$485,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.