Bid Result
35 firms bid on Replace Sidewalks and Curbing at Region 10 - Mental Health Centers for NYS Office of General Services; bids were opened on Wednesday, April 3, 2024. Road Work Ahead Inc was the apparent low bidder at $221,378. The next bid was $284,750, 28.6% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | NYS Office of General Services |
| Solicitation | 47478C |
| Location | Suffolk County, NY |
| Bids opened | April 3, 2024 |
| Bidders | 35 |
| Apparent low | Road Work Ahead Inc — $221,378 |
| Spread | 28.6% (second-low vs. low) |
| First listed | October 20, 2026 |
| Record | RFI-003761 |
Bids opened April 3, 2024. 35 bids. Apparent low bidder: Road Work Ahead Inc at $221,378. Award not yet confirmed.
| Bidder | Bid |
|---|---|
| Road Work Ahead Inc | $221,378 |
| United Paving Corp | $284,750 |
| Laser Industries Inc. | $294,500 |
| Macedo Construction Services | $319,000 |
| KS Construction of NY INC | $420,000 |
| Jiwan Construction Inc. | $433,149 |
| G & M Earth Moving | $437,050 |
| J.S.K Construction Corp. | $467,500 |
| KJB Industries | $474,747 |
| Mark Contracting NY Inc. | $477,000 |
| ZK Ideal Construction Corp. | $497,150 |
| RK Best Construction inc | $510,000 |
| APN Construction Corp. | $533,313 |
| PSL Construction/Industries | $534,485 |
| Bagiana Construction Inc | $540,000 |
| Neptune America Inc | $550,000 |
| Fidelis Contracting Inc. | $572,777 |
| Stasi Industries, Inc dba Gold Coast Pavers | $589,000 |
| Creative Builders, Inc. | $610,400 |
| Deal Concrete | $638,000 |
| Star Construction Industries | $645,169 |
| Minhas General Contractors Company, LLC | $645,823 |
| Tristate Mason LLC | $695,245 |
| Milestone Restoration Inc | $699,500 |
| G-Brothers Contracting Corp. | $715,000 |
| Rubens Group, Inc. | $729,802 |
| Pencol Contracting Corp. | $750,135 |
| Madhu Construction Corporation | $767,700 |
| NorthStar Contracting Corp. | $789,000 |
| Ok Restoration Corp | $795,555 |
| Mac Contractor Inc | $796,736 |
| Preet & D Construction Inc | $834,029 |
| IBEX Contracting Inc. | $920,000 |
| Musa Builder Corp. | $953,836 |
| Northe Group, Inc. | $970,528 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Bid Express → The live bid board
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire