Home › The RFP Wire › RFI-001904
Bid Result
3 firms bid on Structural Repair and Painting from 9th Avenue Portal to Stillwell Terminal, West End Line, in the Borough of Brooklyn (BMT) for MTA Construction & Development; bids were opened on Wednesday, November 19, 2025. TULLY CONSTRUCTION CO., INC. was the apparent low bidder at $309,233,742. The next bid was $322,700,292, 4.4% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | |
| Solicitation | C34938R |
| Trade | Structural steel repair and painting (elevated structure) |
| Location | Brooklyn (West End Line, 9th Avenue Portal to Stillwell Terminal) |
| Bids opened | November 19, 2025 |
| Bidders | 3 |
| Apparent low | TULLY CONSTRUCTION CO., INC. — $309,233,742 |
| Spread | 4.4% (second-low vs. low) |
| First listed | September 3, 2026 |
| Record | RFI-001904 |
Bids opened November 19, 2025; 3 bidders. A+B contract: apparent low on the combined math was Tully Construction Co., Inc. at $309,233,742 evaluated ($304,053,450 price before the schedule value). Awarded to Tully Construction Co., Inc. for $304,567,450 on June 18, 2026.
| Bidder | Bid |
|---|---|
| TULLY CONSTRUCTION CO., INC. | $309,233,742 |
| C A C INDUSTRIES INC. | $322,700,292 |
| GRAMERCY GROUP INC | $537,940,292 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
MTA C&D — Bid Results → The live bid board
Every open bid and bid result from MTA Construction & Development, with how the owner lets its work and where to register.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire