Bid Result
Bids on Engineering Consulting for Brooklyn and Queensboro Bridges for Transportation were opened on Thursday, August 27, 2026. CHI Consulting Engineers LLC was the apparent low bidder at $1,243,369. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | Transportation |
| Solicitation | 84126W0066001 |
| Trade | Construction Related Services |
| Bids opened | August 27, 2026 |
| Apparent low | CHI Consulting Engineers LLC — $1,243,369 |
| First listed | August 27, 2026 |
| Record | RFI-001641 |
Awarded to CHI Consulting Engineers LLC for $1,243,369.
City Record Online (CROL) — Award → The live bid board
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List