13 firms bid on CUNY College of Staten Island Buildings 1A and 2A Entrance Door Reconstruction and AHA for CUNY; bids were opened on Tuesday, February 4, 2025. High Point Construction Group Corp. was the apparent low bidder at $1,532,786. The next bid was $1,582,424, 3.2% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Agency | |
| Bids opened | February 4, 2025 |
| Bidders | 13 |
| Apparent low | High Point Construction Group Corp. — $1,532,786 |
| Spread | 3.2% (second-low vs. low) |
| Record | RFI-001219 |
Apparent low bidder: High Point Construction Group Corp. at $1,532,786 - from bid-opening records, subject to verification and not yet a confirmed award. 13 bids received.
| Bidder | Bid |
|---|---|
| High Point Construction Group Corp. | $1,532,786 |
| IN House Group, Inc. | $1,582,424 |
| B&B Contracting Group | $1,690,244 |
| Jaysan Contracting Corp | $1,800,000 |
| SRR Holdings LLC | $1,845,786 |
| Cube Construction Services LLC | $1,983,551 |
| United Force Construction Corp. | $2,000,000 |
| LO SARDO General Contractors, Inc. | $2,153,000 |
| Maven Restoration Inc | $2,194,320 |
| National Environmental Safety Company, Inc. | $2,333,000 |
| Minhas General Contractors Company, LLC | $2,398,841 |
| Gem Quality Corp. | $2,942,500 |
| Whitestone Construction Corp. | $5,195,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Every open bid and bid result from CUNY, with how the owner lets its work and where to register.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire