7 firms bid on Classroom Addition at Harrison High School; bids were opened on Thursday, March 6, 2025. Pierotti Corp. was the apparent low bidder at $1,912,300. The next bid was $2,147,000, 12.3% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | March 6, 2025 |
| Bidders | 7 |
| Apparent low | Pierotti Corp. — $1,912,300 |
| Spread | 12.3% (second-low vs. low) |
| Record | RFI-001196 |
Apparent low bidder: Pierotti Corp. at $1,912,300 - from bid-opening records, subject to verification and not yet a confirmed award. 7 bids received.
| Bidder | Bid |
|---|---|
| Pierotti Corp. | $1,912,300 |
| Renu Restoration & Contracting | $2,147,000 |
| Kings Capital Construction Group | $2,240,000 |
| Grace Contracting and Development llc | $2,323,000 |
| Nurzia Construction Corp. | $2,350,044 |
| Light House Designs Inc | $2,943,000 |
| National Environmental Safety Company, Inc. | $5,119,000 |