Bid Result

CUNY New York City College of Technology Building E Roof Replacement and AAA

27 firms bid on CUNY New York City College of Technology Building E Roof Replacement and AAA for CUNY; bids were opened on Thursday, March 13, 2025. AARCO Contracting LLC was the apparent low bidder at $754,118. The next bid was $776,786, 3% higher. The apparent low bidder is not the awardee until the owner makes the award.

AgencyCUNY
Bids openedMarch 13, 2025
Bidders27
Apparent lowAARCO Contracting LLC — $754,118
Spread3% (second-low vs. low)
RecordRFI-001188

Apparent low bidder: AARCO Contracting LLC at $754,118 - from bid-opening records, subject to verification and not yet a confirmed award. 27 bids received.

BidderBid
AARCO Contracting LLC$754,118
Sajid Contracting Corp.$776,786
SRR Holdings LLC$789,786
Mason Construction Services Inc$937,200
Vad Contractors Inc$960,000
Avenue Contracting Inc.$990,000
Ok Restoration Corp$1,055,555
Echostar Construction, Inc.$1,098,000
ZHN Contracting Corp$1,147,050
Euro Castle Construction Corp.$1,197,306
Lima Contractors Corp.$1,272,000
Prograde Construction Inc.$1,285,800
Cube Construction Services LLC$1,314,716
Alliance Tri-State Construction, Inc.$1,330,000
Sienia Construction Inc$1,342,750
B N Restoration Inc.$1,359,786
AKSH Quality Contracting Corp.$1,372,800
ABCD Construction Corp$1,399,999
Apollon Group, LLC$1,455,705
Hardrock Construction Corp.$1,511,230
Attri Enterprises Inc.$1,534,727
N.B.A Construction Inc$1,605,000
Pb Contracting Corp.$1,645,000
LO SARDO General Contractors, Inc.$1,656,000
Atlantic Specialty Inc$1,886,000
ICB Contracting$1,906,000
JM&A Construction Corp$2,423,064

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Recent results from CUNY

Every open bid and bid result from CUNY, with how the owner lets its work and where to register.

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire