Bid Result
9 firms bid on PS 198 (K) FY24 Reso A (MA) Cafeteria Upgrade, Path of Travel; bids were opened on Tuesday, May 27, 2025. Worldnet Construction was the apparent low bidder at $701,000. The next bid was $710,994, 1.4% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | May 27, 2025 |
| Bidders | 9 |
| Apparent low | Worldnet Construction — $701,000 |
| Spread | 1.4% (second-low vs. low) |
| Record | RFI-001102 |
Apparent low bidder: Worldnet Construction at $701,000 - from bid-opening records, subject to verification and not yet a confirmed award. 9 bids received.
| Bidder | Bid |
|---|---|
| Worldnet Construction | $701,000 |
| Brikmor, Inc. | $710,994 |
| Archinova Builders LLC | $723,954 |
| BCR Construction Corporation | $760,000 |
| JPR Builders 07 Inc. | $795,000 |
| On Top Renovation Inc. | $797,127 |
| Where To Get It Services, LLC | $805,000 |
| Shining Sky Inc. | $819,000 |
| Bullay Shah Inc | $846,638 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List