Bid Result
4 firms bid on PS 98 (M) Non-TCU Removal-Mini Building, Path of Travel; bids were opened on Monday, June 2, 2025. Jaysan Contracting Corp was the apparent low bidder at $2,547,000. The next bid was $2,745,000, 7.8% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | June 2, 2025 |
| Bidders | 4 |
| Apparent low | Jaysan Contracting Corp — $2,547,000 |
| Spread | 7.8% (second-low vs. low) |
| Record | RFI-001078 |
Apparent low bidder: Jaysan Contracting Corp at $2,547,000 - from bid-opening records, subject to verification and not yet a confirmed award. 4 bids received.
| Bidder | Bid |
|---|---|
| Jaysan Contracting Corp | $2,547,000 |
| Honey Construction NY, Inc | $2,745,000 |
| N.B.A Construction Inc | $2,910,000 |
| F&S General Construction, Inc. | $4,490,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List