Bid Result
6 firms bid on R. Carson HS for Coastal Studies 344/IS 303 (K) Reso A Room Conversion, Path of Travel; bids were opened on Monday, June 9, 2025. Arora Construction Inc. was the apparent low bidder at $1,626,000. The next bid was $1,785,000, 9.8% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | June 9, 2025 |
| Bidders | 6 |
| Apparent low | Arora Construction Inc. — $1,626,000 |
| Spread | 9.8% (second-low vs. low) |
| Record | RFI-001050 |
Apparent low bidder: Arora Construction Inc. at $1,626,000 - from bid-opening records, subject to verification and not yet a confirmed award. 6 bids received.
| Bidder | Bid |
|---|---|
| Arora Construction Inc. | $1,626,000 |
| OM General contractors corp. | $1,785,000 |
| Shaheen Construction Corp | $1,844,000 |
| Sega Contracting Corp. | $2,079,000 |
| Maestro Construction Corp. | $2,800,000 |
| Approved General Contracting Inc. | $2,820,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.