Bid Result
18 firms bid on PS 89 (Q) Air Handling Units, Fire Alarm Replacement, Ventilation, Roofs, Windows, Flood Elimination, Exterior Masonry; bids were opened on Monday, June 9, 2025. Armstrong Roofing Corp. was the apparent low bidder at $17,470,000. The next bid was $18,611,000, 6.5% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | June 9, 2025 |
| Bidders | 18 |
| Apparent low | Armstrong Roofing Corp. — $17,470,000 |
| Spread | 6.5% (second-low vs. low) |
| Record | RFI-001049 |
Apparent low bidder: Armstrong Roofing Corp. at $17,470,000 - from bid-opening records, subject to verification and not yet a confirmed award. 18 bids received.
| Bidder | Bid |
|---|---|
| Armstrong Roofing Corp. | $17,470,000 |
| Roma Scaffolding | $18,611,000 |
| Zarco Contracting Inc. | $19,627,000 |
| Adam's European Contracting, Inc | $19,718,000 |
| KG Construction Services, Inc. | $19,825,000 |
| Venus Group, Inc. | $19,927,000 |
| Nehal Contracting, Inc. | $20,426,000 |
| Corbex, Inc. | $20,790,000 |
| Skyline Industries LLC | $21,364,000 |
| National Environmental Safety Company, Inc. | $21,666,000 |
| P&K Contracting Inc. | $22,475,000 |
| ABC Construction Contracting, Inc. | $22,628,000 |
| Whitestone Construction Corp. | $22,891,000 |
| Northeast Restoration Corp | $23,200,000 |
| Positive Electrical Associates, Inc. | $23,880,000 |
| Kel-Tech Construction, Inc | $24,800,000 |
| Neelam Construction Corp. | $25,990,000 |
| BQE Industries, Inc. | $29,500,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.