2023 Capital Bond Project Phase 1 at Hawthorne Elementary School

4 firms bid on 2023 Capital Bond Project Phase 1 at Hawthorne Elementary School; bids were opened on Tuesday, September 9, 2025. ADP Group Inc. was the apparent low bidder at $6,184,000. The next bid was $6,292,700, 1.8% higher. The apparent low bidder is not the awardee until the owner makes the award.

Bids openedSeptember 9, 2025
Bidders4
Apparent lowADP Group Inc. — $6,184,000
Spread1.8% (second-low vs. low)
RecordRFI-000944

Apparent low bidder: ADP Group Inc. at $6,184,000 - from bid-opening records, subject to verification and not yet a confirmed award. 4 bids received.

BidderBid
ADP Group Inc.$6,184,000
Pierotti Corp.$6,292,700
Piazza, Inc.$6,412,000
APS Contracting, Inc dba Asphalt Paving Systems$7,540,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.