2023-2024 Capital Improvement Program at Memorial Education Center, Jonas E. Salk MS, Summit Lane ES and Macarthur HS - Phase 3E,3F

8 firms bid on 2023-2024 Capital Improvement Program at Memorial Education Center, Jonas E. Salk MS, Summit Lane ES and Macarthur HS - Phase 3E,3F; bids were opened on Thursday, November 6, 2025. AFL General Construction Inc was the apparent low bidder at $1,435,250. The next bid was $1,497,000, 4.3% higher. The apparent low bidder is not the awardee until the owner makes the award.

Bids openedNovember 6, 2025
Bidders8
Apparent lowAFL General Construction Inc — $1,435,250
Spread4.3% (second-low vs. low)
RecordRFI-000888

Apparent low bidder: AFL General Construction Inc at $1,435,250 - from bid-opening records, subject to verification and not yet a confirmed award. 8 bids received.

BidderBid
AFL General Construction Inc$1,435,250
Renu Restoration & Contracting$1,497,000
Ashlar Contracting$1,524,000
W.J. Northridge Construction Corp.$1,574,000
JNH Construction Group Inc.$1,672,000
Mount Olympos Restoration LLC$1,673,000
Stalco Construction, Inc.$1,720,000
Irwin Contracting Inc.$1,810,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.