8 firms bid on 2022 Bid Bond Capital Improvement Project at South Orangetown Middle School and Tappan Zee High School; bids were opened on Thursday, November 20, 2025. Mount Olympos Restoration LLC was the apparent low bidder at $1,713,000. The next bid was $1,875,399, 9.5% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | November 20, 2025 |
| Bidders | 8 |
| Apparent low | Mount Olympos Restoration LLC — $1,713,000 |
| Spread | 9.5% (second-low vs. low) |
| Record | RFI-000877 |
Apparent low bidder: Mount Olympos Restoration LLC at $1,713,000 - from bid-opening records, subject to verification and not yet a confirmed award. 8 bids received.
| Bidder | Bid |
|---|---|
| Mount Olympos Restoration LLC | $1,713,000 |
| Montana Contracting | $1,875,399 |
| ADP Group Inc. | $2,116,000 |
| Vinco Builders, LLC | $2,149,000 |
| APS Contracting, Inc dba Asphalt Paving Systems | $2,226,000 |
| Renu Restoration & Contracting | $2,363,000 |
| Bertussi's Plumbing, Heating & Cooling Contracting | $2,801,410 |
| GL Group Inc. | $3,250,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.