5 firms bid on Reconstruction Work at Multiple School District Buildings; bids were opened on Tuesday, February 10, 2026. Pierotti Corp. was the apparent low bidder at $8,630,020. The next bid was $8,675,309, 0.5% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | February 10, 2026 |
| Bidders | 5 |
| Apparent low | Pierotti Corp. — $8,630,020 |
| Spread | 0.5% (second-low vs. low) |
| Record | RFI-000806 |
Apparent low bidder: Pierotti Corp. at $8,630,020 - from bid-opening records, subject to verification and not yet a confirmed award. 5 bids received.
| Bidder | Bid |
|---|---|
| Pierotti Corp. | $8,630,020 |
| Renu Restoration & Contracting | $8,675,309 |
| Piazza, Inc. | $8,777,000 |
| Vinco Builders, LLC | $9,239,000 |
| Iron Sword Enterprises, Llc | $10,440,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List