The RFI Wire

Home › The RFP Wire › RFI-000535

Bid Result

2021 Bond Issue Related CIP at St James Elementary School, Mount Pleasant Elementary School, Tackan Elementary School- Phase 2 & 3 -Rebid

4 firms bid on 2021 Bond Issue Related CIP at St James Elementary School, Mount Pleasant Elementary School, Tackan Elementary School- Phase 2 & 3 -Rebid; bids were opened on Wednesday, April 15, 2026. Stalco Construction, Inc. was the apparent low bidder at $964,000. The next bid was $1,093,000, 13.4% higher. The apparent low bidder is not the awardee until the owner makes the award.

Bids openedApril 15, 2026
Bidders4
Apparent lowStalco Construction, Inc. — $964,000
Spread13.4% (second-low vs. low)
RecordRFI-000535

Apparent low bidder: Stalco Construction, Inc. at $964,000 - from bid-opening records, subject to verification and not yet a confirmed award. 4 bids received.

BidderBid
Stalco Construction, Inc.$964,000
Renu Restoration & Contracting$1,093,000
Irwin Contracting Inc.$1,310,000
Crossroads Construction Corp$1,327,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire