Bid Result
8 firms bid on Alternate Learning Center at Adlai E. Stevenson Educational Campus OS 996/450 (X) FY24/25 Reso A Library Upgrade; bids were opened on Monday, May 4, 2026. S N K Contracting LLC was the apparent low bidder at $1,523,400. The next bid was $1,630,000, 7% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | May 4, 2026 |
| Bidders | 8 |
| Apparent low | S N K Contracting LLC — $1,523,400 |
| Spread | 7% (second-low vs. low) |
| Record | RFI-000513 |
Apparent low bidder: S N K Contracting LLC at $1,523,400 - from bid-opening records, subject to verification and not yet a confirmed award. 8 bids received.
| Bidder | Bid |
|---|---|
| S N K Contracting LLC | $1,523,400 |
| Sega Contracting Corp. | $1,630,000 |
| North East Atlantic Business Solutions Corporation | $1,800,000 |
| Muzi Construction Corp | $1,824,000 |
| Major Contracting Inc | $1,920,000 |
| DN Construction Services, Inc | $1,947,000 |
| Satnaam International Construction Corp. | $1,995,000 |
| Maestro Construction Corp. | $2,888,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire