Richmond Hill HS 475 (Q) Exterior Masonry, Windows, Supporting Structural Elements, Roofs, Parapets

20 firms bid on Richmond Hill HS 475 (Q) Exterior Masonry, Windows, Supporting Structural Elements, Roofs, Parapets for NYC School Construction Authority; bids were opened on Wednesday, June 3, 2026. J & N Construction Group Corp. was the apparent low bidder at $15,996,000. The next bid was $16,826,000, 5.2% higher. The apparent low bidder is not the awardee until the owner makes the award.

AgencyNYC School Construction Authority
Solicitation26-22900D
TradeExterior Envelope / General Construction
LocationRichmond Hill HS, 89-30 114th Street, Queens
Bids openedJune 3, 2026
Bidders20
Apparent lowJ & N Construction Group Corp. — $15,996,000
Spread5.2% (second-low vs. low)
RecordRFI-000427

Apparent low bidder: J & N Construction Group Corp. at $15,996,000, one of 20 bids. SCA's tab shows the contract awarded to the apparent low.

Our coverage

BidderBid
J & N Construction Group Corp.$15,996,000
Nehal Contracting, Inc.$16,826,000
Army Construction, Llc$17,057,000
Faith Construction, Inc.$17,222,000
Carnak Construction Inc.$17,970,000
Pro-Metal Construction, Inc$19,167,000
KOKO Contracting, Inc.$19,180,000
CVM Construction Corp$19,400,000
Allcon Contracting Corp$19,476,000
Zarco Contracting Inc.$19,555,000
Maven Construction Corp.$19,652,000
Whitestone Construction Corp.$19,871,000
Skyline Industries LLC$20,346,000
BQE Industries, Inc.$20,400,000
Sea Breeze General Const. Inc.$21,617,000
KG Construction Services, Inc.$21,700,000
Venus Group, Inc.$21,759,000
Kel-Tech Construction, Inc$22,000,000
Ashnu International, Inc$23,773,919
Neelam Construction Corp.$27,779,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

NYCSCA Bid Tabulation Search Tool → The live bid board

Recent results from NYC School Construction Authority

Every open bid and bid result from NYC School Construction Authority, with how the owner lets its work and where to register.

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List
© The RFI Wire