4 firms bid on Fort Hamilton HS/PS 490 (K) Walk-In Refrigerators and Freezers; bids were opened on Tuesday, June 9, 2026. Nola Construction Inc. was the apparent low bidder at $1,022,400. The next bid was $1,070,739, 4.7% higher. The apparent low bidder is not the awardee until the owner makes the award.
| Bids opened | June 9, 2026 |
| Bidders | 4 |
| Apparent low | Nola Construction Inc. — $1,022,400 |
| Spread | 4.7% (second-low vs. low) |
| Record | RFI-000402 |
Apparent low bidder: Nola Construction Inc. at $1,022,400 - from bid-opening records, subject to verification and not yet a confirmed award. 4 bids received.
| Bidder | Bid |
|---|---|
| Nola Construction Inc. | $1,022,400 |
| Creative Form Development, LLC | $1,070,739 |
| Bharat Mechanical Corp | $1,150,000 |
| Madhu Construction Corporation | $1,566,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · All records · All projects · Get The Punch List